Decision details

KILCHRENAN PRIMARY SCHOOL

Decision status: For Determination

Is Key decision?: No

Is subject to call in?: No

Decisions:

A report updating the Committee on the current situation of Kilchrenan Primary School and inviting Members to agree to the recommendations outlined was considered.

 

Decision

 

The Committee agreed that:

 

1.    Kilchrenan Primary School be mothballed on a temporary basis and that the building be retained for two years on a care and maintenance basis;

 

2.    Officers would prepare a review of the school’s mothballing for the Committee’s March 2023 meeting at which Members could decide on a continued period of mothballing or request Officers to begin a preliminary exercise with a view to starting the pre-consultation process to consider the future options for Kilchrenan Primary School; and

 

3.    The community would have pre-arranged access to the building to promote community functions during the period of mothballing.

 

(Reference: Report by Executive Director with responsibility for Education dated 10 March 2022, submitted)

Publication date: 16/03/2022

Date of decision: 10/03/2022

Decided at meeting: 10/03/2022 - Community Services Committee

Accompanying Documents: