Queen's Hall Regeneration - Property Acquisition
Report by Regeneration Project Manager
:
Minutes:
Members considered a report outlining the current status of
the property acquisition process and associated costs involved in the purchase
of the affected properties.
Motion:
That the Area Committee
ask the Council for additional funds to bring the contingency funding for this
project to a suitable level as agreed by
the Project team.
Moved by Councillor Breslin,
seconded by Councillor Blair.
Amendment:
To agree the recommendations outlined at section 2.0 of the
submitted report.
Moved by Councillor Walsh, seconded by Councillor Marshall.
Decision:
On a show of hands vote the Amendment was carried by 5 votes
to 2 and the Area Committee resolved accordingly.
(Ref: Report Executive Director of Development and Infrastructure Services, dated 3rd June 2014, submitted).
: