CAMPBELTOWN CHORD BERTHING FACILITY
Recommendation from Mid Argyll, Kintyre and the Islands Area Committee held on 5 November 2014 and Report by Executive Director – Development and Infrastructure Services
:
Additional documents:
Minutes:
The Council considered a recommendation from Mid Argyll, Kintyre and the Islands Area Committee in respect of the CHORD Campbeltown Berthing Facility Project.
Decision
Agreed the recommendations detailed at paragraph 3 of the Executive Director’s report.
(Reference: Extract from Minutes of Mid Argyll, Kintyre and the Islands Area Committee of 5 November 2014 and report by Executive Director – Development and Infrastructure Services dated 3 November 2014, submitted)
:
Campbeltown CHORD Berthing Facility
Update by Project Manager.
:
Additional documents:
Minutes:
The Committee considered a report outlining the progress to date in the delivery of the CHORD Campbeltown Berthing Facility Project with specific information on the tendered cost and the critical timeline for completing the project.
Discussion took place in relation to a number of matters contained within the report.
Decision:
Members agreed to refer to Council approval of the
recommendations detailed at paragraph 3.1 of the report.
(Ref: Report by Executive Director of Development and Infrastructure Services, dated 5 November 2014, submitted.)
: