9 ROTHESAY PAVILION PROGRESS REPORT PDF 12 MB
Report by Project Manager, Rothesay Pavilion
:
Minutes:
The Committee gave consideration to a progress update
report on the
Rothesay Pavilion Adaptive Restoration and Extension Works project.
Decision
The Bute and Cowal Area
Committee:-
1.
Considered and noted the progress
update provided in the report and;
2.
Noted the new Project Manager,
Jonathan Miles, took up post on the 23rd July 2018.
(Ref:
Report by Rothesay Pavilion Project Manager dated 4th September
2018, submitted)
:
9 ROTHESAY PAVILION PROGRESS REPORT PDF 3 MB
Report by CHORD Programme Manager
:
Minutes:
The Committee considered a progress update report on the Rothesay Pavilion Adaptive
Restoration and Extension Works project following completion of the funding
package in September 2017 and the award of the construction contract to Messrs
CBC Ltd in November 2017.
Decision
The Committee considered and
noted:
1.
The Rothesay Pavilion Adaptive
Restoration and Extension works contract had been fully funded with an
anticipated final cost of £13,991,536
2.
The contract had been awarded to
Messrs CBC Ltd who remain on schedule to complete on 31st July 2019.
3.
The Project Manager left the
Council on 4th May 2018 to take up a new post with Highlands and
Islands Enterprise (HIE).
(Ref: Report by CHORD Programme
Manager dated 5th June 2018, submitted)
:
ROTHESAY PAVILION PROGRESS REPORT
Report by Rothesay Pavilion Project Manager
:
Minutes:
The Committee considered a progress update report on the Rothesay Pavilion Adaptive
Restoration and Extension Works project.
Decision
The
Committee:
1. Noted the contents of the
report
2. Noted the recommendations at
2.1 and 2.2 of the submitted report
3. Requested a regular update
paper and officer representation be brought to Area Committee for the duration
of the project and;
4. Requested a representative of
the Rothesay Pavilion Charity be invited to the next Bute and Cowal Business Day.
(Ref:
Report by Rothesay Pavilion Project Manager dated 6th March 2018,
submitted)
: