Report by Head of Development and Economic Growth
Minutes:
The
Chair welcomed everyone to the meeting which was held on a hybrid basis. For the purposes of the sederunt Stuart Mclean,
Clerk to the Committee today, read out the names of the Members of the
Committee and asked them to confirm their attendance.
In
advance of the meeting today interested parties confirmed they would make
presentations to the Committee. Mr
McLean read out the names of those representatives and asked them to confirm
their attendance. Mr McLean also
clarified from one other objector in attendance that they would like to speak.
The Chair referred to the PPSL Committee held on 20 March
2024 when it was:
1. noted that the Committee were
satisfied in relation to conditions 2, 3, 6, 7, 8, 9, 13, 15, 16 and 17; and
2. agreed to hold a
pre-determination hearing on a Hybrid basis in relation to conditions 11 and
12.
The Chair advised that this hearing was being held to
consider conditions 11 and 12 and to determine the application in full
following that consideration. He
explained the hearing procedure that would be followed and invited the Senior
Planning Officer to present the case.
PLANNING
On
behalf of the Head of Development and Economic Growth, David Moore, Senior
Planning Officer, made the following presentation with aid of power point
slides.
General Introduction
Members
will recall that at their last meeting on 20th March 2024 they were
satisfied with all Approval of Matters Specified in Conditions (AMSC)
submissions made, with the exception of those related to conditions 11 and 12
on drainage and flooding design.
Additional
clarification on these matters was sought by Members at that meeting. However, Planning Officers were not qualified
to provide this technical advice and therefore a hearing to examine these
specific matters in more detail was determined by Members to be required.
With
respect to supplementary report 1, this updates members on submissions since
their last meeting on 20th March and concludes that the
recommendation of officers to approve the AMSC submission details in respect of
conditions 11 and 12 matters (and all other matters that were before the
Committee) has not changed.
Members
will note a number of exchanges on Friday 14 June 2024. All of these exchanges have been copied to
them and nothing within them alters the views of Officers as set out in the
main report and supplementary report 1.
In response to these submissions the Applicant has also submitted a
further e-mail submission on 14 June 2024 clarifying that:
The attachments to the email to which Mr Gatensby refers
were simply: his own objection; the eplanning receipt to confirm submission of
the updated DSR (which purely updated the layout therein, as explained in your
Supplementary Report); and a copy of your own email requesting comment. There
was no additional technical information included in that email, and the
‘drainage calculations’ referenced are those within the original DSR – there
were no new calculations provided or attached in that communication, and
therefore all the ‘technical facts’ have been available since the original
Planning Committee meeting.
The
Council’s drainage and flooding advisor has re-examined the exchanges and
reconfirmed on 14 June 2024 that he remains of the opinion that no objection to
the proposals should be raised.
I
now have a very brief, presentation, on the matters the hearing has been called
to discuss. I have kept my presentation brief as I am aware that the Applicant
intends to present a more technical presentation to cover the issues to hand.
Slide 1 - Original Layout
submitted
Eastern Boundary. Through discussions with the
Applicant a revised layout was agreed that resolved both Roads and Planning
Officer concerns.
Slide 2 Revised Layout
The previous line of houses on the eastern boundary
has been broken up and driveway and access arrangements altered to meet the
requirements of the area roads engineer. This revised layout has been
incorporated into the drainage strategy
report (Issue 5) and does not alter its conclusions.
Slide 3 - Drainage and
SUDS (Sustainable Urban Drainage Development System) Layout
This represents the overall general layout of
drainage for the site. An interceptor trench along the northern boundary will
collect water flowing to the site from land above it and be discharged to land
to the west of Darleith Road. The water within the site will be collected in a
SUDS pond and released via a separate discharge to land to the west of Darleith
Road. Foul water will be discharged to the mains sewer network and to Scottish
water treatment works.
There are a number of technical submissions in
support of this approach.
I now have a series of photographs which set out
some general views of the site from Darleith Road and the land to which the
water will be discharged.
Slide 4
Satellite image showing application site and area of
land to the west where the two surface water outfall pipes will be discharged
before flowing down to the pond area and then to the Geilston burn.
Slide 5
Looking south from the proposed entrance on Darleith
Road. SUDS pond location to left hand
side.
Slide 6
Looking east across the site.
Slide 7
Looking North with area where discharge will be made
on left hand side of Darleith Road.
Slide 8
One of the existing drainage features on the land to
the east of Darleith Road which drain to the existing pond and then into the
Geilston Burn.
Slide 9
Local Development Plan - online plan extract perhaps
more clearly gives a general indication of the existing drainage
characteristics of the land where the surface water will be diverted to. The
extract also shows the pond area and Geilston Burn which this pond feeds into.
The Glen residential property is also indicated on this plan.
Conclusion
Officers remain of the opinion that necessary design
details, and supporting technical information has been provided to demonstrate
that the proposals before Members are acceptable and meet required drainage and
flood attenuation standards for the proposed development.
On this basis Officers and their expert advisors
consider that the details submitted to discharge conditions 11 and 12 are
acceptable and therefore details in respect of conditions
2,3,6,7,8,9,11,12,13,15,16 and 17 as submitted under application 23/00144/ AMSC
should be approved, and the conditions discharged as per officer
recommendation.
APPLICANT
Andrew
Phillips gave the following presentation with the aid of power point slides:
Thank
you for your time today.
The
site is an allocated housing site by Argyll and Bute Council and can deliver
118 units of which 30 are affordable.
Following
the planning meeting on 20th March, it was agreed that the application
information satisfactorily addressed the conditions but that further clarity on
Conditions 11 and 12 was required. Conditions 11 and 12 relate to flooding and
drainage.
I am
here today to provide an understanding of the drainage and flooding proposals
for the proposed new Cala development in Cardross.
We
acknowledge there have been concerns raised by neighbours of the development
which we have addressed separately and furthermore we hope the information
provided today will clear up these concerns. The drainage report being
discussed was undertaken by Dougal Ballie Associates, acting as lead consultant
for Cala.
The
original designs for the drainage outfall for this development were based on
the Avant homes proposals as well as a review of Scottish Water’s existing
services drawings.
This
design shows the outfall from the on-site SUD’s basin traveling down Darleith
Road and connecting into the existing installed Scottish Water surface water
sewer. Scottish Water had been consulted on the outfall and the outfall was
deemed as “A1” meaning based on their records this sewer was exactly as shown
on the plans.
We
then set out to prove the sewer was in as per the drawings. This process is
done by mobile CCTV camera.
The
results of this investigation found that the existing Scottish Water sewer had
not been installed and that the surface water for the properties off Kilmahew
Avenue had been wrongly connected to the combined sewer network.
Further
discussions with Scottish Water took place to try and resolve the outfall issue
where it was proposed that we have one final check within the ground of
Cardross primary. No outfall was located.
At
this stage both Cala and Scottish Water concluded that there was not a suitable
surface water connection for the development and that an alternative outfall
would need to be established. The original outfall position was not considered
due to the 19m level difference from the road to the Geilston Burn creating a
significant health and safety risk to construct.
Scottish
Water recommended that the best solution for an outfall for the development
would be to create a three-pipe network. This means there would be a dedicated
pipe installed solely to serve the surface water flows wrongly connected at
Kilmahew Avenue as well as the usual surface and foul pipework to services the
development.
This
approach would give CALA our outfall while taking away the flow of water
entering the combined sewer network within Cardross. In terms of Scottish water
policy removing surface water from the combined sewer network is the first and
preferred option.
To
allow this to be considered as a solution two checks were required;
Check 1. CALA had to provide Scottish
Water with the flows and water quantity that would be removed from the downstream
combined system verified by a 3rd party flood model.
Check
2. CALA were also to analyze the effects of the additional surface water flow
being discharged to the Geilston burn and submit this to the council for
approval, showing there was no additional flood risk.
The outcome to point 1, a review of the
flooding within the Cardross wider network, was that there was a betterment to
the flooding within the Cardross in 3 historic flooding locations by a
considerable volume.
The locations
of existing historic flooding being improved were at the side of the tennis
lawn and at the existing football pitch.
The
outcome to point 2 the flooding report reviewing the Geilston burn was
submitted to the council in June 2023 and approved by the council’s independent
design checker JBA with no objections.
Important
Technical information from the approved flooding report.
To
discuss this section, it helps to have an understanding of freeboard. Freeboard
is the maximum designed flooding level plus 600mm and is the standard provision
for any new build house being constructed across all councils in Scotland.
The
Glen, Geilston Court and Rockwell Cottage has a freeboard of 1.9m when modeled
with the flooding flows. Over 3 times the planning requirements.
In
the gardens of Burnsland, Greenacre and St Mahews where existing flooding is
predicted the change in flood level is only +/- 6cm. Therefore, there is no
increased flood risk to these dwellings.
The
Existing Pod
The pond contains a permanent volume of
water, and the level in the pond is controlled by a weir. The flows from
Kilmahew Avenue and the development site pass through the pond and out to the
watercourse via a cascade. This pass through of flow will have very minimal
impact on the water level in the pond as the weir is the controlling factor.
The current situation for the site's
surface water runoff is that these flows go to the low point of the field
discharging onto Dareith road cascading down the road causing flooding within
the road corridor. The proposed new drainage and SUDS would contain this flow
within the development and prevent it spilling onto Darleith road. Therefore,
it is a betterment.
The
surface water drainage within the new development has been designed to National
SUDS design guidance. This means the flows leaving the development must match
or better the flows leaving the field.
Surface
water flows discharging from the development site are controlled via a
hydrobrake flow control device. Flows greater than the discharge rate is
attenuated within the site via a SUDS attenuation basin.
Scottish
Water has issued a full technical approval for these drainage proposals. This
means they are satisfied with the designs and have provided a statement for
this committee in support of the proposals.
This
statement summarizes that Scottish Water view the proposals to remove the
surface water from the combined network as an ideal opportunity to work with
Cala to deliver improvement and return the surface water to the Geilston burn
as intended.
“In this instance, the proposals
to separate the surface water from Kilmahew Ave represents an ideal opportunity
for Cala and Scottish Water to work together to rectify an apparent error in
the constructed sewer network when these properties were built, as historic
sewer records indicate that this surface water was always intended to discharge
to the Geilston Burn.”
Mark
McCullagh – Development Manager Scottish Water
In
conclusion the proposed development site can deliver 118 much needed family
homes of which 30 being affordable.
The
proposal put forward will discharge surface water from Kilmahew Avenue to the Geilston
burn. This will remove volume from the combined sewers therefore reducing the
frequency of foul drainage spills within Cardross.
The
discharge of flows from Kilmahew Avenue and the proposed development pose no
additional flood risk proven by DBA flooding report and approved by the
council’s independent design checker.
The drainage solution proposed is the
preferred option of the governing body Scottish Water who have issued a
technical approval for the proposals.
The
details presented today are based on factual information and data which has
been included in the flood report.
Following
the drainage investigations Scottish water could independently install the 3rd
pipe system under statutory powers to remove the surface water from the
combined network even if the Cala’s development does not proceed. Cala are
looking to facilitate these works and minimize disruption to the local
community.
Thank you for your time today
CONSULTEES
Cardross Community Council
Patrick Trust
Patrick
Trust advised that he was the current Convener of Cardross Community
Council. He said that when he first came
to Cardross more than 40 year the Community Council were opposed to any
developments in Cardross and the reason for this was all the raw sewage went
from the public toilets straight out into the Clyde at low water. The Community Council removed their
objections to developments in Cardross when Scottish Water built a new pumping
station at the site of the public toilets which took all the sewage from the
village to Dumbarton. He advised that
they were not opposed to new developments and recognised the housing emergency
in Argyll and Bute. However, it has now
been recognised that Scottish Water gained approval in October, which the
Community Council complained about, to put in an overflow sewage drainage
system in Cardross Park as the current system was unable to cope with flooding
in the village. He said that this
overflow was going to have untreated sewage entering the Geilston Burn, taking
us back 40 years and was unacceptable.
He advised that the reason Scottish Water were approving all this was
they had a bypass system currently under construction and were going to put
raw, untreated matter into the Geilston Burn to prevent the flooding currently
experienced.
Lynsey Young
Lynsey
Young advised that she was the Vice Convener of Cardross Community Council and
gave the following presentation with the aid of power point slides.
Argyll
and Bute Council in this area followed the Scottish Environmental Protection
Agency’s (SEPA’s) Flood Risk Management Plan for Clyde and Loch Lomond Local Plan
District.
This
states the following -
In
2015 the objectives were split into two categories which were defined as:
• Reduce
overall flood risk: to reduce the risk of flooding from all sources
(river, sea and surface water) as far as reasonable, taking account of
economic, environmental and social priorities.
• Avoid
an increase in flood risk: to avoid increasing flood risk through land
use planning and maintenance of existing flood management infrastructure.
It
has a section on land use and spatial
planning which states that one of the most powerful tools available when
creating a sustainable flood risk plan is to align how you are using land with
the flood risk. It goes onto point out that decisions relating to flood risk
management can have significant implications for the location of development
and, likewise, decisions relating to the location of development can impact on
flood risk.
SEPA
is a key agency in the land use planning process with a duty to cooperate with
planning authorities in the preparation of development plans and have a
statutory role to provide flood advice for appropriate development management
applications. The advice they give seeks to promote flood avoidance. In
addition, land use planning objectives and actions have been agreed with
responsible authorities, which will ensure flood risk is adequately considered
in local planning decisions
Finally,
local authorities are responsible for working together to produce Scotland’s
local flood risk management plans and work in partnership with SEPA, Scottish
Water and other responsible authorities. It is the responsibility of local
authorities to implement action to manage flooding and maintain flood defences.
So as a Community Council we have concerns that SEPA have not been involved to
date with this proposed development.
SEPA’s
message is clear: “More rainfall will mean places could flood more often and
increase the chance of severe flooding from surface water and rivers. Rising
sea levels will increase the risk of flooding from the sea.”
So
this is pertinent to Geilston Burn, which the proposed site plans to discharge
into. There is a weir which is at least 50 years old and we are not convinced
it is going to work.
Let
me talk though what is on the screen currently. The two maps compare downstream
flooding from land run off with coastal flooding when high tide combines with
strong winds, seen twice in the last year.
These both show flooding around the bottom of the village, where we have
a railway and a cycle path bridge as well as community facilities by way of a
park, tennis courts, not to mention people’s houses! This certainly matches up
with our lived experience in the village. The top right shows December 2022 at
that site. You can see the railway line
in the distance and the cycle path bridge in the foreground. Anecdotally this
level was higher in October 2023. The video on the right shows up stream of the
village and shows the volume of water heading down the road towards the
burn.
Norman
will show more detail around the proposed discharge into the Geilston National
Trust for Scotland Pond which drains into the Geilston Burn. As a council we
wanted to highlight another aspect which concerns us about increasing this
discharge. This pond is currently infested with American Skunk Cabbage which is
classed as an invasive species by the Scottish Invasive Initiative. We would ask why has an environmental impact
assessment not been done increasing the flow of water into the burn from the
pond as ‘these seeds are dispersed by water ways’ (Scottish Invasive
Initiative). It is hard work to control and eradicate skunk cabbage and again I
quote ‘Although initial invasions will expand slowly, once this plant takes
hold it can spread rapidly and become a serious problem’. We are happy to share
with anyone more information about Skunk Cabbage, but the bottom line seems to
be that we should be careful not to introduce it into a burn which has native
flora and fauna.
Norman Gatensby
Norman
Gatensby gave the following presentation with the aid of the power point
slides.
My name is Norman Gatensby, I
live at The Glen on Darleith road, a property my wife and I purchased 2 years
ago. I am going to talk about the technical analysis on which the council are
making their decision as it relates to the drainage strategy and flood risk.
I hold a master's degree in mechanical
engineering and I have worked in the built environment/construction industry
for about 10 years. I am a managing associate director for a consultancy,
leading an engineering team who work across residential, healthcare, higher
education, and public sector projects. We design systems to provide heating,
cooling, ventilation, hot/cold water and drainage. I am not a hydrologist, but
I am comfortable reviewing and understanding technical reports.
I believe that the points I
will raise today will demonstrate that the analysis within the reports
submitted on behalf of Cala, is insufficient, inconsistent, inaccurate and
requires additional investigation.
The conclusions that Dougall
Baillie have drawn are based on the results of digital modelling which relies
on approximations and estimates to represent the built and natural environment.
I believe that those approximations and estimates have not accurately accounted
for the problems that the village faces with respect to flooding on a regular
basis.
One of the main reasons for
this is the mismanagement of the drainage serving the Kilmahew development.
This was intended to be piped through the school grounds, underneath Darleith
Road, and discharged into the Geilston Burn at the bottom of the The Glen’s
garden. That pipe is shown on Scottish Water's asset plans and a previous
version of the drainage strategy for the proposed new development was to
connect into that pipe. Upon investigating, Scottish Water determined that the
pipe does not exist. Instead, the water that was supposed to be discharged into
the Geilston Burn is diverted into the combined sewer at the top of Barrs Road,
overwhelming the system, and contributing to significant flooding down Barrs
Road and the A814 - the main road into and through Cardross. The resultant
flooding and the fact that Scottish Water were evidently not informed or
consulted on that change is clear evidence that the construction of the
drainage system serving Kilmahew was completely mismanaged by those involved, resulting
in significant and persistent risk of flooding. I urge Argyll and Bute Council
to not allow that to happen again.
With that in mind, I would like
to draw your attention to two points made by Dougall Baillie in their Geilston
Burn Flood Study. The first point states that there is no risk of flooding to
the three properties listed, on the grounds that the burn will not break its
banks, and the water level will be 2m lower than the properties. I have measured the level of the burn
recently at 1.7m lower than The Glen during a dry spell. As you will see in a
moment, sustained heavy rainfall presents a very real risk of the burn breaking
its banks.
The second point concludes
that three different properties are at risk of flooding. At this point it's
worth repeating the points Lindsey made about Argyll and Bute Council following
SEPA's flood risk management plan whose objectives are to reduce, and avoid
flood risk. It's also worth pointing out that the Argyll and Bute Local
Development Plan Policy 55 states that where the potential for flooding is
identified, the planning authority should exercise the precautionary principle. Dougall Baillie have concluded that only the
gardens of these properties are at risk of flooding, but I would ask who would
be liable for the damages done to those properties if the approximations and
estimates used in the analysis prove to be wrong. It is not fair for residents
to have to deal with the consequences of irresponsible decision making as we
are the ones who will have to pay for repairing flood damage.
Slide 7
The images you see on screen now are of the
Geilston Burn, around Node 5 of the Dougall Baille digital model. These were
taken at the rear of The Glen, which is approximately 8m from the bank of the
burn. The image on the left was taken a couple of weeks ago and shows the burn
at a normal level for this time of year, the path on the far bank is part of
the Geilston Gardens walking route which is used regularly. The video I am
about to play was taken in October, with the burn in full flow, inches from flooding
our house. Note that the burn has burst its banks and the Geilston Gardens path
is completely submerged, as you can see in the image on the right. During that
storm, the pond connected to the burn also burst its banks. The risk of the
burn flooding The Glen is far higher than the Dougall Baillie reports have
concluded.
Slide 8
The pipe highlighted in blue in this image is
proposed to divert the water from Kilmahew into the Geilston Burn. The pipe bypasses the SUDs and the hydrobrake
which limits the flow of water into the burn, so the flow of water in this pipe
is unmanaged and unregulated. If this
system was proposed for a new development, it would not be permitted as it
would contradict policy 61 of the Argyll and Bute Local Development Plan which
states all development proposals will manage all rain and surface water through
Sustainable Urban Drainage systems.
Dougall Baillie have pointed out that the drainage system serving
Kilmahew does not form part of the new development and is not subject to the
same conditions. However, that pipe is
included on the Dougall Baillie drawings and connects to the infrastructure
that serves the new development, so I would argue that it should be subject to
the same stringent risk reductions.
Slide 9
As you can see on screen the calculations
provided by Dougall Baillie offer no clarity as to what flow rate from Kilmahew
they have assessed. They state on page 15 of their Flood Study that the flow
from Kilmahew generates a peak flow of 155.3 litre per second (l/s), however in
their response to my objection they state the peak flow assessed is 388.6 l/s.
These numbers may be hard to visualise, so for clarity 388.6 l/s would fill a
6-lane, 25m swimming pool such as the one in Helensburgh Leisure Centre, in less
than 25 minutes. Given the volume of water in question, and the fact that it is
not limited by a hydrobrake, it is vitally important that clarity is given, and
the precautionary principle is applied.
Slide 10
The map in the centre of the screen shows the
village with the proposed development superimposed. The video you are seeing
was taken at the top of Barrs Road, in the southeast corner of the proposed
development. The next video was taken at the intersection of Barrs Road and
Ritchie Avenue, looking uphill towards the proposed development. As you can see
this is a massive volume of water, which requires a stringent and detailed risk
based approach to be adopted when addressing it.
Slide 11
The
drainage strategy is for the surface water from the proposed development and
Kilmahew to be combined, and discharged into a pond which feeds into the
Geilston Burn.
The
image on the left shows the full extent of the digital model created by Dougall
Baillie, beginning upstream from The Glen and Geilston Gardens at Node 1, and
terminating near the train tracks near the Clyde at Node 21.
The
image in the middle focuses in on a specific section of the model, between
Nodes 1 and 7. The pond that is proposed to be the connection point has been
omitted from the model, in fact, the analysis assumes that the connection point
is directly into the Geilston Burn, meaning that the digital model does not
reflect what is shown on the drawings.
The
image on the right shows the extents of the topographic study referenced by
Dougall Baillie in their Drainage Strategy. As you can see, the pond was also
omitted from this analysis. The pond is uphill from, and behind our house. Its
capacity has not been assessed, and the Dougall Baillie drawings state that an
additional topographic survey is required to confirm the suitability of the
proposal. I would ask why neither a hydrological or topographic survey has not
already been undertaken, and why Argyll and Bute Council have not insisted on
such analysis being done prior to this point. In my opinion, it would be unsafe
to discharge these conditions until such time as these issues are fully
resolved. The weir that has been talked
about is rusted and has not been used in about 30 or 40 years.
Slide 12
The
image on the left shows the pond in question. As you may be able to see, and
hopefully witnessed yourselves during a site visit, the pond is in a very poor
condition and has not been maintained for decades. It has several fallen trees in it and a lot
of vegetation including American Skunk Cabbage, as Lindsey noted this is an
invasive species spread in waterways. No
environmental impact assessment of the pond has been undertaken. The image on the right clearly shows that the
outfall into the pond is outside the red line boundary of the proposed
development. No evidence has been
provided that Cala have reasonable expectations of acquiring that land, or the
rights to use it. The land owner – The
National Trust for Scotland – have shared with me that they have no intentions
of allowing any additional water to be diverted into the pond. Additionally, no
evidence has been provided that Scottish Water would approve a section 3 order
under the Sewerage Act. I would ask why Argyll and Bute Council are promoting
such a proposal without the appropriate consents provided.
Slide 13
The
image on the screen now shows some of the calculation settings that govern the
Dougall Baillie digital model. The settings I have highlighted shows that the
maximum time of concentration for the assessment is 30 minutes. I am not sure
how many of you live locally, but I personally don’t remember the last time it
rained for only 30 minutes. The west coast of Scotland faces storms lasting for
days, not minutes, and this is another approximation that suits a digital
model, but does not reflect reality.
Slide 14
As
you have heard SEPA are not a statutory consultee when it comes to discharging
conditions of planning conditions which have been granted permission. If the current design, however, had been
submitted as part of the original planning application, SEPA would have been a
statutory consultee. So, whether it is
legally required or not, it is right and proper for SEPA to be consulted. Excluding SEPA demonstrates contempt for the
organisation responsible for flood risk management in the country.
Lynsey Young
Slide 5
We
have now looked at the directly affected burn in some detail. To finish we
would like to add further detail about the flooding in the village. Barrs Road
runs from the east side of the proposed development down to the main road. This
main road is the only way in and out of our village to and from Dumbarton and
Helensburgh, other than the small B roads that run uphill of the village. In
October 2023 this road was very close to being unpassable, which is a situation
we are keen to avoid happening again or being made worse.
Slide 15
In conclusion we would ask
elected Councillors to consider a holistic view when making a decision today,
and consider the following;
-
That the evidence put before you by Cala is at this stage insufficient
because;
-
Longer term rainfall events have not been considered.
-
The capability of the burn to drain at high tide has not been assessed.
-
The volume of water passing uncontrolled into the burn, bypassing the
hydrobrake, has been quantified.
-
Neither the volumetric capacity of the Geilston pond, or the
environmental impact of the proposed design, have been assessed.
-
Residents of the village seek assurance from Argyll and Bute Council
that their homes won’t be at further risk of increased flooding as a result of
this proposed development.
It is the responsibility of
Argyll and Bute Council to protect the residents of Cardross from the risk of
flooding.
Patrick Trust
Slide 19
I
hope you have the opinion of Cardross Community Council on the flooding. This picture was taken at the closed cycle
path. This shows water at the rail
bridge in December 2022. There are
yellow and red markers on the rail bridge put by Scotrail. The water has been consistently above the
yellow mark on at least 3 occasions over the last 2 years. But due to the railway line being underwater
at Bowling we have not had to notify Scotrail.
The burn is at capacity. Sadly at
the moment in the park just behind this picture, Scottish Water are working to
prevent sewer flooding by putting the excess water in the park directly into
the burn through a sieve. I would
suggest to the Committee that we are returning to the position when I first
came to Cardross over 40 years ago when sewage was put straight into the
Clyde. Scottish Water are now doing that
again.
SUPPORTERS
Councillor
Gemma Penfold gave the following presentation:
Members, thank you for
allowing me to speak at today’s hearing. In June of last year we, as
a Council, were the first local authority to declare a housing emergency and I
stand firmly behind that declaration and will do what I can to bring about
solutions to tackle the local housing crisis.
As a councillor for the Helensburgh and Lomond South Ward I am very
aware that this Cala Homes project is a controversial topic.
We are extremely lucky here
in Argyll and Bute to be surrounded by such a beautiful landscape and the last
thing anybody wants is to cover that beauty with buildings. I understand that, however, we need to
look at the bigger picture here and as a community we need to understand that
there is a large proportion of people in the area who are living in overcrowded
or unsuitable homes, if they have one at all. I have received
numerous emails from constituents who are at their wits end with their current
living situations but have no hope of getting themselves and their families out
of that situation due to the lack of housing in the area. Issues
such as overcrowding within homes, poor quality existing housing stock and lack
of homes, in general, can negatively impact both economically and socially and
can have a very adverse effect on our local residents and their mental
health. For example, cramped or
unsuitable living conditions can harm family relationships, negatively affect
children’s education, and cause stress, anxiety and depression for individuals
and families which can sometimes take people out of the workforce. New housing brings an opportunity to
alleviate these pertinent issues and bring about the opportunity for people to
thrive.
I recently met with the Naval
Families Association, and they too recognise the impact that the lack of
housing is having on current, and former serving military personnel who, due to
the lack of housing in our area, are having to move themselves and their
families out to West Dunbartonshire and not able to stay in areas closer to
their base. This also affects family
members who may need to change jobs or schools because of this
move. Our towns and villages benefit greatly from our forces
families living here and I know the majority of them absolutely love Argyll and
Bute with many families moving here and choosing to put down roots because of
the friendships and support they receive throughout the
community. It’s a sad day when they have to uproot and start again
in a new area that’s further out and not specifically designed to support the
forces families because of a lack of housing here in Helensburgh and
Lomond.
It is okay to sit with your
feet up on your couch in your forever home, that you worked hard to buy, or to
lie comfortably in your bed in a rented property that you enjoy living
in, saying that you don’t want a new housing development built for whatever
your own personal reason is. But the
reality of it is, we desperately need new housing in the area. My own family was lucky enough to get our
first mortgage only 4 short months before COVID hit but, like so many families,
if we had waited just a few months longer, we would have been in a position
where our savings dwindled, mortgage rates went up, house prices went up, and
we wouldn’t of been in any position to get on the property
ladder. This situation didn’t happen to us but it did happen to
plenty of other people. Since then we are enduring a cost of living
crisis and the social housing list in Argyll and Bute has soared to over 3000
applicants. The Cala homes site in Cardross would be providing 30
affordable homes, which could help provide a route to home ownership for 30
people or families that are otherwise not in a position to buy a
home. This is an incredibly important step to helping us tackle the
housing crisis.
This site was allocated by
the Council in 2015 and deemed suitable for a housing development. It is clear
to me that there have been issues since then but Cala’s proposals appear to be
tackling the main issue of flooding that was one of the original causes for
concern. The Council’s own flood officer and Scottish Water both
confirm that this is the case and therefore I have confidence in supporting
this application.
Lack of housing is an all too
familiar story in Helensburgh and Lomond and I don’t see a way forward unless
we start to allow housing to be built in suitable areas. For this
reason, I fully support Cala’s application today and, after meeting with them
on several occasions, I am confident that they are offering a robust housing
delivery plan that will provide us with both private and affordable
housing. I would ask that the Committee approve Cala’s application
today so we can take the first small step to tackling the housing crisis that
we declared a year ago.
Thank
you for your time.
OBJECTORS
Morag Elliot
Morag
Elliot advised that she was also speaking on behalf of her husband. She said that she did not have the technical
knowledge but did live in the village.
She advised that no one would argue that there was a lack of housing and
that housing was needed in the village but not at any cost.
She
said she did not have the same confidence, as Cala were a private sector
organisation and may not necessarily have the community’s interests at
heart. The primary objective of a
private sector organisation is to maximise profit and answer to
shareholders. Argyll and Bute Council
have a duty to provide housing so they have a vested interest to get places
developed and to do it in a way that delivers for the community but not at any
cost.
She
referred to the long term consequences of flooding and said it was not a one
off event. She referred to householders
down south that 20 to 30 years ago lived in villages that did not have a big
flooding problem but now could no longer get house insurance. She said they did not want to get to that
same position here. She said that anyone
that has worked with numbers knows that they can very much get them to say what
you like.
She
said that it was really important that the Committee have all the relevant
information from as many sources as they could.
She advised that the Committee had information from the Council, the
Applicant and their experts. She asked
why SEPA were not consulted. She said if
the answer is because they did not have to be consulted and it is not the law,
then that was not appropriate.
She
advised that she expected the Committee to act on behalf of the community and
stressed that they were concerned about the flooding implications – such as the
mess that has to be cleared up, damp, and the ability to sell their houses. She asked why the pond has not been looked at
and advised that the pond and Geilston Burn were not fit to have any more water
going into it.
She
said she had no confidence on the data provided by a private sector
organisation who have nothing to gain but profit. She pointed out that the Committee have been
presented with a lot of information that they would have to manage. She said that as a voter she expected her
Councillors to assess the data in its entirety and ask questions on her behalf
and to make sure all avenues were explored before taking any decisions to change
the shape of the village forever. She
said that SEPA needed to be consulted and an environmental impact assessment
needed to be carried out.
Julie Lang
Julie
Lang advised her home was called Ellismore and it was on Darlieth Road and was
adjacent to and right next door to the proposed development.
She
said that in her neighbourhood they did not have mains sewerage and that each
house in her little community had a septic tank. The run off water from the septic tanks went
into a very small burn parallel to the road.
This little burn has not been mentioned yet and it drained across the
fields opposite the site and went into the Geilston Burn. She said she had concerns when that floods.
The
field in front of her house and the development already flooded on a regular
basis when there were periods of heavy rain.
She said she was concerned about any additional drainage of water into a
system, which could barely cope at the moment.
She said it was affected by the tides.
She advised that if there was a Spring tide, which happens every month,
and a southerly wind parts of the village were already being flooded. Although Argyll and Bute Council needed to
build new homes, she said they needed to ensure this did not cause damage to
the existing community.
Jacquelyn McInally
Jacquelyn
McInally referred to it being said that the flood water went out of the pond
via a weir and said this did not happen.
She said that last year they were inundated at the burn with water
coming out the back of the pond. It came
out the back of the pond to their kitchen area that there was so much water
coming down the road.
She
referred to having an open section of a wall and explained that it had not been
closed yet as she’d had private contractors assess it and they have said that
as it was a Council asset it was their responsibility. She advised that the Council have said it was
not their responsibility to fix it because they did not think it was their part
that was broken therefore it had to stay open.
She
referred to the proposal that water now be channelled into the burn and advised
that if it had already been channelled there at the moment she was in no doubt
that her house would have been flooded.
She advised that the way in which it flooded last year, meant that it
came through the air vents and under their house which had been renovated over
the last 2 years.
She
said that they have tried to make representations to the Committee and through
Councillor Kennedy. She said she was
thankful for Councillor Kennedy’s assistance to get this hearing organised. She advised of contacting lawyers and a
hydrologist. She advised that they had
said it was not feasible for her as an individual to get the level of studies
done to have confidence in this plan.
She said that they needed help to make sure this was looked at
fully. She said she was not trying to
suggest that people did not want people to move into Cardross. They just wanted to make sure it was safe and
that the investments they have made in the village were not going to be
entirely lost.
She
advised that if all the water the Committee saw in the videos which came down
Barrs Road and Darleith Road had been re-directed into the burn and it broke
its banks at the National Trust Land, that it would have flooded her home. She advised that the hydrologist she had
spoken to had advised that while this was the formal approach to the assessment
of flooding, the over simplification of this case was not appropriate as it did
not consider all rainfall events. The
pond has not been modelled and no one knows how it will behave under additional
water pressure. She advised that the
National Trust and herself were co-owners of the burn. She advised that they owned up to the half
way point of the burn and were responsible for the maintenance of that. She said she did not want to be responsible
for the maintenance of a burn that was going to have all this additional water. She pointed out that the Roads (Scotland) Act
said quite clearly that developers and individuals were not allowed to increase
the burden on owners and that is what was happening under this plan. The field behind the burn where it was
proposed to dump the water into an existing weir cannot cope. The animals housed in this field are
sometimes stuck and have to be helped out and come through their garden
sometimes. She advised that it was
entirely reckless to suggest this and the Council really needed to sort it out.
Tom McInally
Tom
McInally thanked the Committee for the opportunity to speak and advised he had
nothing much to add to the objection raised by the Community Council and
thanked them for their presentation. He
advised that he was a Planning Consultant with 38 years experience in planning
and that he had never come across a situation where there was a planning
application for houses without the actual road solution incorporated within the
red line boundary.
He
said that no planning application has ever been considered for this road. He said there was a red line but there had
never been any official statement, any official public consultation with the
community or anybody else.
He
said that planning conditions were only normally attached if the Applicant
owned the land, or if there was a reasonable expectation that what was being
built would have the approval of the owners.
He advised that in this case it was very doubtful. He suggested the roads condition could be
ultra viras, outwith the law, and challengeable by Judicial Review.
He
advised that on the application plan it showed a pipe connection on Darleith
Road over his client’s land. He said
that on inspecting the site they found that there was no outfall, no manhole
cover and through that they contacted Scottish Water and it was found that the
Kilmahew site was developed contrary to conditions. He said the public were expected to have
confidence in the planning system and the guardians of this were the Committee
who were expected to protect the interests of their constituents, in this case
the residents of Cardross.
He
said that he had never seen anywhere in Scotland the principal that you could
put flood water on someone’s land without their permission. He said that the National Trust for Scotland
were not going to give that permission.
He said that he was amazed in this case that confirmation from the land
owner to allow this to happen was not required.
He questioned whether this was legal.
He
said that the Council needed to think long and hard about whether this was a
practical solution.
Bob Murray
Bob
Murray referred to Councillor Penfold’s support for this development.
REPRESENTATIVE
Ruth Lightbody
Ruth
Lightbody gave the following presentation:
I live on Barrs Road in
Cardross and saw the flooding of October 2023 first hand. The water came over
my car tyres which is parked on the street and we had to clear the debris from
under the tyres before we could use it. I was unable to take my two small
children out safely and the flooding meant that any of my neighbours with
mobility issues, mobility buggies or prams were unable to venture across the
road – such was the force of the water.
To me, this means that the
flooding and the development are separate issues and that the flooding in
Cardross should be fixed before any consideration is given to this development
which may exacerbate this problem. I do not accept that rerouting all the water
sources into the Geilston Burn will suffice. Nor do I accept that Cala are
doing Cardross residents a favour by fixing this issue – the Council should be
fixing it anyway.
The strength of opposition in
Cardross to this development would be better represented here today if the
public hearing wasn’t being held on a Monday morning. I myself have had to take
time off work to attend. Many of my neighbours have work or other responsibilities
so couldn’t attend today.
People opposing the
development today should not be accused of NIMBYism (which I believe that
Councillor Penfold is insinuating) for being worried about the flooding and the
impact to their quality of life and damage to property. The Councillor’s point about this development
being necessary to meet social housing targets is nonsensical given that (at
the most) only 30 social houses will be included and most of the houses are 3,
4 and 5 bedroomed houses designed to be sold to the wealthy. We need a sensible
social housing strategy and this is not it.
MEMBERS’ QUESTIONS
Councillor
Brown expressed her concern about flooding and commented that she did not feel
all the information they had been provided with was satisfactory. She said she had concerns about the water
going to be channelled out across someone’s field. She also expressed concern about the Skunk
Cabbage without any extra water coming across. She asked the Applicant what
they were going to do about that. The
Applicant advised that the site currently discharges to that other field and
that they would be attenuating the water and restricting it to the one and two
year Greenfield run off. At present it
has an uncontrolled Greenfield run off.
By putting in the drainage this will control the release of water from
the site in accordance with all National Planning Policy and will reduce the
discharge of peak run off from the site.
Councillor
Brown referred to the increased flooding and commented that this would not be a
one off event and sought comment from the Applicant on how they would manage
that. The Applicant advised of the
design being in accordance with guidance.
Councillor
Green referred to there being two aspects to this - drainage from the site and
drainage from the new connection from the other part of the village and asked
Planning if both of these aspects were being conditioned. Mr Moore advised that all aspects were being
considered.
Councillor
Hardie sought and received assurance from the Applicant that the development
would not contribute to the worsening of flooding in Cardross. The Applicant confirmed that the design was
compliant with the guidance and will not make the flooding worse as a result of
the development.
Councillor
Philand asked why SEPA have not been involved.
Mr Moore explained that SEPA were consulted on the original application
in 2015 which stems from application 15/01394/PPP and they responded in July
2015. This was for a planning permission
in principle. They identified that the
site was subject to flooding, did not object, and indicated that any future
proposal should mitigate and have regard to surface water flooding on the site. Mr Moore confirmed that the design put
forward by the Applicant seeks to mitigate the flooding on the site. He advised that there was no requirement to
consult with SEPA on additional discharge matters. The submission made to the Committee today is
that this issue has been addressed.
Mr
Cameron advised that in respect of planning matters, SEPA will only really come
in on river flooding and flooding from the sea.
Surface water was for the local authorities to look at. Even though they do surface water mapping,
SEPA will not look at it from a planning point of view and it has been that way
for a number of years now. Mr Moore
added that SEPA have published a triage document of when they should be
consulted and when they should not.
Councillor
Philand sought and received an explanation from the Applicant on how the SUDs
scheme would work. The Applicant advised
that they would not be discharging anything greater than the Greenfield run off
at the moment. The Applicant said that
the design had been modelled and had been physically looked at on the
ground. The run off from the site goes
into the ditch they were proposing to discharge to from the site. They would not be adding any extra flow, they
would be reducing it.
Councillor
Kennedy sought and received confirmation from the Applicant that they would not
be increasing the amount of water being channelled, they were changing the flow
to go round the site rather than through it.
Councillor
Kennedy referred to ownership of the field opposite the site and asked the
Applicant why they were proposing to discharge water onto someone else’s
land. The Applicant advised that the
water already discharged there and that they were not changing anything.
Councillor
Kennedy sought and received confirmation from the Applicant that the sewage
would go through a new pipe network to a Scottish Water combined sewer at the
bottom of Darleith Road. It was
confirmed that the road would be dug up to install this pipe network.
Councillor
Green referred to the road being dug up and asked if more pipe work could be
installed to discharge at other points.
The Applicant advised that this had been looked at but due to
engineering considerations it was not possible.
Councillor
Irvine advised that he had real concerns that no permission had been received
from the landowner to discharge the water and the damage this could cause
including the potential for land erosion.
He also expressed concern about there being no hydrologist report and
topographical issues. He asked the
Applicant how confident they were to be able to mitigate against the potential
impact of water, which was now going to be channelled away from site to protect
the housing estate, to very specific hot spots which may not protect the
outlying areas. The Applicant advised
that they have designed this in accordance with the guidance. In terms of run off from the site, it runs off
to Barrs Road and Darleith Road. By
draining the site and controlling the run off it will reduce what contributes
to these factors. Reference was made to
the videos showing the water running down Barrs Road and it was pointed out
that this road would be upgraded to adoptable standards and will have road
gulleys on it, which don’t currently exist to catch surface water. The videos showing water running off the
site this water will all be channelled in the SUDs basin. There will be considerably less water flowing
down the road when this development is complete.
Councillor
Irvine asked why written permission had not been received from the National
Trust for Scotland. The Applicant
advised that Scottish Water were confident that they would get the approval to
go ahead and discharge at that location.
They advised they did not believe they needed landowner approval as it
was an improvement of the Scottish Water network. Scottish Water have a statutory power to do
this work even if the Cala development did not go ahead and have intimated that
they would do that.
Councillor
Irvine asked Ms McInally, as part owner of the burn, if she had been approached
to give permission to have the run off going into the burn. Ms McNally said they had not. She advised that they had contacted Cala to
show them their position and flooding experience at the moment.
Councillor
Irvine asked Ms McInally if she, as part owner, had an ongoing relationship
with the National Trust for Scotland and did she know if they had granted
permission for this work to go ahead. Ms
McInally advised that a survey had been done of the burn. She said that the water coming down Barrs
Road and Darleith Road would now come into the burn. She referred to damage already done to the
wall of the burn which was just under their kitchen window.
Councillor
Howard asked the Applicant why no consultation had taken place with the owners
of the land. The Applicant explained
that the water from the site currently goes there and that they were putting in
the necessary drainage to ensure the water no longer goes there and this has
been approved by Scottish Water.
Councillor
Kain asked the Applicant if he was right in his understanding that with their
works on this they would improve upon existing faulty drainage. The Applicant confirmed that was correct.
Councillor
Kain asked the Applicant to confirm that with this development there was going
to be better drainage from that site and around it. The Applicant confirmed they were removing a
misconnected surface water connection to the combined sewer which caused
flooding problems in Cardross at the moment.
Councillor
Kain sought and received confirmation from the Applicant that they were
improving a situation that was improperly designed in the first place. The Applicant pointed out that this was
totally unrelated to this development.
This was an existing issue that has been resolved.
Councillor
Green asked the Applicant how it was possible for them to control the combined
volume of water from the Kilmahew site and this development site to ensure
there would be no greater run off than there was at the moment. The Applicant advised that they were in
control of what was on their site and in terms of the misconnected surface
water connection at Kilmahew, that should have originally gone to the burn when
those houses were built but was never connected. They were now providing the conveyance
through to get the water where it should have went. The Applicant advised that was a separate
issue to the development. It was
providing Scottish Water with a means to get the water from A to B.
Councillor
Green sought and received confirmation from Planning that this was all being
considered as part of this hearing. The
Applicant referred to the detail of this being in the flood risk assessment and
that they were reinstating what Scottish Water should have built and the flow
of water back to where it should have been going.
Councillor
Brown sought and received confirmation from the Applicant that they will have
control of the water coming off their site.
Water coming from elsewhere will be a matter for Scottish Water. The Applicant pointed out that the water
coming down the Darleith Road and Barrs Road was not just associated with this
development site and that they could not control what came down from further up
the hill and that the water the developer will be discharging will be
controlled.
Councillor
Kennedy expressed his concern about various places being flooded now and his
fears about the increase of water that would be channelled. He also referred to the septic tank in
Geilston Park. Patrick Trust pointed out
this was approved by the Council back in October. The Community Council did raise objections
and SEPA were consulted by Argyll and Bute Council and this overflow to the
sewage was discussed. He said it was not
SEPA’s preferred option what Scottish Water were going to do. They would prefer a proper pipe under the
railway line of the right size and to have all the sewage and surface water
pumped to Dumbarton. He advised that
SEPA were not entirely happy with what Scottish Water were now doing at the
park, which was, to cope with the overflow, to sieve sewage and water into the
burn. The problem was the burn was
tidal and when the tide was high the water had nowhere to go. He said that Scottish Water have gone against
advice from SEPA and the Council have rubber stamped the decision to put raw
sewage into the burn. He said all of
this was connected. He said that this had not been properly assessed and that
there was a need to look at the whole situation of water in Cardross before
adding to the problem.
Councillor
Wallace asked if any consideration had been given to directing this into
the attenuation tank. The Applicant advised no as it was
unassociated to the development. He said
they were just providing the means for Scottish Water to install what should
have been built. Anything to be
associated with that drainage would have to be out with the site where the
houses were located.
Councillor
Wallace asked if it would be possible to direct a pipe into the tank. The Applicant explained that technically it
may be possible but it would require whole redesign which was not associated
with this development and was a problem Scottish Water already had in that
area.
Councillor
Blair referred to the slides presented by Cardross Community Council showing
the volume of water going into the burn and sought and received confirmation
from the Applicant that it would not be possible increase the size of the SUDs
basin. The Applicant confirmed that
Scottish Water have granted technical approval for this. If this was built Scottish Water would then
adopt and maintain the sewers in perpetuity.
We have a design based on the size in accordance with their
guidance. They won’t accept something
bigger than it has to be as they would then have an asset that they would need
to maintain at additional cost. It was
designed up to the 200 year climate change limit which was all that they would
permit. The Applicant advised that their
hands were tied by Scottish Water as they would be adopting and maintaining the
sewer network on completion of the network.
Councillor
Green referred to the drainage from Kilmahew which should have gone into the
burn many years ago and noted that this was just putting in place what should
have been done many years ago. He sought
and received confirmation from Planning that if that development was just
happening now that design would not be acceptable.
Councillor
Green asked if the Committee were being asked to approve something that would
not be acceptable as a new development now.
Mr Moore advised that the Committee were being asked to approve an
application before them which met all the required standards. He advised that planning would not approve
that type of drainage system now, however, what the application seeks to
propose is to attenuate that which can be attenuated for the scheme and model
that, and to provide a betterment to an existing sub-standard situation in
terms of the drainage that is causing flooding further down the combined
sewer. On that basis, and the fact that
it forms part of this application, and no harm has been found through the
reports that have been submitted to other interests that was why Planning were
content.
Councillor
McCabe sought and received confirmation from the Applicant that this was to
correct a problem with the water and flooding which was not from this
development but from something that happened before this development was
proposed and that they had their own plans in place for their development.
Councillor
Howard expressed concern about damage to the burn and how this would be
maintained. The Applicant reiterated
that they were reinstating where the water should have went. A modelling exercise has been undertaken and
demonstrates that with the water in it would make no difference to the flooding
and so no increase to property risk as a result of that water going in.
Councillor
Philand referred to the Mr Trust’s comments about raw sewage within the system
and asked why this should be accepted.
The Applicant advised that this was an issue for Scottish Water and was
not part of the development.
Councillor
Philand referred to the invasive species and asked why an environmental impact
assessment had not been done. Mr Moore
advised that this would have been requested when the Planning Permission in
Principle was applied for and already granted.
He said that invasive species was dealt with under separate legislation
and was not a straightforward planning matter.
Councillor
Irvine asked Planning if consideration had been given to commissioning a
hydrologists report. He commented on the
significant concerns from objectors in terms of a whole range of impacts. Mr Cameron advised that in terms of the
technical submissions on hydrology, flooding and drainage he found these to be
acceptable and came up to the required standards and that is why he did not
submit an objection.
Councillor
Irvine advised of concerns that a holistic approach had not been taken and that
it was clear from the lived experienced shown that there was significant risk
of flooding now. He asked from a
planning perspective and also from the Applicant how a road map could be
created going forward that would take a far more holistic view and look at
comparing the lived experience with the data modelling.
The
Applicant advised that they could not undertake a holistic approach to all the
flooding issues that were happening in Cardross. They advised that they have demonstrated that
they have complied with all the guidance for developing the site.
Councillor
Irvine pointed out to the Applicant that they would now be channelling water
which previously would have, to a degree, soaked away and found other
routes. The Applicant advised that
there was a ground source pipe flowing currently under the road. Talking about the infiltration of rain that
was going out via pipes under Darleith Road.
Mr
Moore referred to the question of a holistic approach and advised that in terms
of a planning application there was a limit to what the planning authority
could seek to address town or village wide issues in relation to the
application. What planning were required
to do was deal with flooding which was related to the proposals in order to
comply with necessary standards. No one
knows why that pipe was not provided in the past but there was going to be
wider benefit to the communities in terms of reducing the amount of water in
the combined sewer. So by chance there
was a wider benefit of this associated with this application. He said they could not ask the Applicant to
look at all the flooding and that it was really for the Council to look through
its local flood plans and regional flood plan strategies. He said that they had a team of engineers
that were looking to deal with flooding and also Development Management who
they could talk to about potentials and opportunities for mitigation. He said it would be unreasonable to request
the Applicant to look at the whole situation.
Councillor
Irvine asked if it would be reasonable to go back to SEPA as 9 years have now
passed to seek a consultation responsenow.
Mr Moore said no, mainly because they would not respond as the
application does not meet their criteria for responding. Their response in 2015 identified a flood
risk on the site and they required the Applicant to address the surface water
on the site and the proposal before us today does and has been agreed by those
with technical expertise.
Councillor
Irvine asked if any of the objectors had any dialogue with SEPA. Mr Gatensby advised that SEPA had informed
them that they were consulted on the original design which basically put water
into an existing pipe. He pointed out
that as the design has changed they should be consulted again.
Councillor
Irvine asked Planning to respond. Mr
Moore advised that he did not think it met the criteria to consult SEPA. The issue that was identified was on surface
water and that has been addressed.
Councillor
Irvine referred to comments made that the design had changed since the original
application. Mr Moore advised that there
was no design before as it was a planning permission in principle application. He said there was no design to approve and
that SEPA just advised that the surface water drainage needed to be addressed.
Councillor
Kennedy referred to the original application and asked where the water
discharged into. The Applicant advised
that the water discharged down Darleith Road into the Scottish Water sewer and
Geilston Burn as the pipe that should have been there was not built. He confirmed that they were now providing a
means to put this through the development site.
Councillor
Kennedy commented that what existed now was as it had been for years and
questioned whether it would be better to leave it alone. The Applicant advised that the current
situation was what was causing the combined flooding issues further down the
village. They advised that they were
helping Scottish Water to solve one of their problems by providing them with a
means to fix one of their pipes. The
Applicant stressed they were not creating the issue but where providing a means
to rectify an issue on Scottish Water’s network.
Councillor
Brown questioned why Scottish Water were not at the hearing. She sought and received confirmation from the
Applicant that Scottish Water would adopt their SUDs regardless of that pipe
being in or not.
Councillor
Brown asked what would happen if the solution did not work once all the plans
were in place and the water went above and beyond what was there just now. She asked who would fix that problem. The Applicant advised that their report had
demonstrated that would not happen and that they only had to design the scheme
to set guidance. Scottish Water would be
responsible for the pipe network and the SUDs going forward.
Councillor
Blair commented that the men were just doing their job to the best of their
ability on the site. He suggested that
this would be great place for a hydro scheme and would be a holistic approach
to dealing with the water. He added that
what the Committee were dealing with here was an application with two elements
to approve. He said that he thought the
Officers and Applicant had done their best to answer questions and address the
issues raised by the community and suggested the Committee move on to the next
stage of the proceedings.
Councillor
Green advised that he was mindful that the Committee needed as much information
as possible before moving onto the debate.
Councillor
McCabe said that she agreed with Councillor Blair. She advised that she thought this was an
application for a housing development and everything was concentrating on
previous flooding. She said the
Committee needed to look at the application as the flooding that was there was
the flooding that was there before. She
commented that the country was in a housing emergency and that the developers
have put forward as much as they could and had been very helpful.
Councillor
Green sought and received confirmation from the Committee that they had no
further questions.
The
Chair ruled, and the Committee agreed to adjourn the meeting at 1.05 pm.
The
Committee reconvened at 2.00 pm and it was established that all Members of the
Committee that were present at the meeting this morning had returned to the
meeting.
SUMMING UP
Planning
Sandra Davies advised that this
was an application for the approval of conditions following the grant of
planning permission in principle.
The purpose of this hearing was to
allow Members to consider the flooding and drainage issues relating to
conditions 11 and 12 of the planning permission in principle.
These conditions were ones where
the planners required the advice of their advisors on flooding and
drainage. She confirmed that they have
been advised that the submission by the Applicant was acceptable and accorded
with the current guidance.
It was therefore recommended that
these conditions be discharged.
Applicant
Andrew
Phillips advised that this site was an allocated Housing site which had been
assessed by all statutory consultees with no objections received. The SUDs design managed all flood water
linked to this development through this application in front of the Committee
today. He further advised that in
addition they were installing a missing section of drainage pipework from the
Scottish Water network that would improve the existing flooding situation
downstream to Cardross unrelated to this development. In terms of landownership, the outfall was
being installed under statutory powers and had been approved by Scottish Water
and the Council’s flooding expert who was a hydrologist. If this development did not proceed Scottish
Water could under statutory powers continue to install the drainage network.
Consultees
Cardross Community Council
Norman
Gatensby summed up as follows:
I would like to start by stating that the Cardross Community Council has
no objection to the development, or the provision of affordable housing in
principle. The objections we have presented relate to the way that the
development is being proposed.
Councilors have asked pertinent questions but looking at your reactions
to the answers, it seems that those answers have not alleviated your concerns.
We have heard statements by Dougall Baillie Associates and the Applicant
that the quantity of water proposed to be directed to the burn will not
increase. The water from the development is passing through a hydrobrake to
control the flow of water into the burn, but the water from Kilmahew is being
redirected to the burn, and not through a SUDs pond or hydrobrake.
As shown in our presentation, the burn is breaking its banks without the
water from Kilmahew being redirected to it, so it’s illogical to state that
adding the water from Kilmahew doesn’t increase the flood risk. The quantity of
water being directed to the pond, by natural or mechanical means, will
absolutely increase from its current levels.
While it’s true that Scottish Water won’t accept an oversized SUDs
basin, they may consider a redesign of the SUDs to incorporate the Kilmahew
water. I’d urge Councillors to take the precautionary principle in light of the
confirmation from the Planners that the system being proposed to service
Kilmahew would not, if proposed today, be acceptable.
The history of Kilmahew clearly demonstrates that when corners are cut,
and changes are made without proper review and consultation, the consequences
can be dire. Therefore, we would again ask that SEPA be consulted on the
revised design.
As we’ve heard earlier, SEPA operate a triage system to reduce the
burden on them. This includes guidance that if developments comply with a
specific set of rules, known as the General Binding Rules, SEPA are not a
statutory consultee. The original design, connecting to an existing Scottish
Water outfall, complies these rules. The new design, does not. I’m going to
quote now from the Water Environment (Controlled Activities) (Scotland)
Regulations 2011:
Email From NTS:
“Regarding the Cala homes development, we have informed Cala Homes that
we do not want to proceed with the water pipe they proposed as we do not want
any extra water to go into the burn from their development. We have since been
informed that they have found another option anyway to take the water in
further downstream so it doesn’t need to have anything to do with us going
forward.”
From Tim Keyworth, Gardens and Design Landscape Manager (West and
Arran).
Lynsey Young
Lynsey
Young referred to the points brought up about being holistic in this case and
advised she recognised what had been said.
She said that she would like to highlight the changing environment and
referred to the Scottish Government having 15 consequences of climate change in
Scotland with point number 5 being an increased risk of flooding. She said that flooding could already have a
devastating effect on those affected and with climate change would likely alter
rainfall patterns and bring heavier down pours and increase to flood risk in
the future was expected. This could
impact on properties and infrastructure with serious consequences for our
people, heritage, businesses and communities.
She advised that there was a need to think outside the box. She said she respected everyone here today
doing their individual jobs. She asked
where the body was that pieces all this together and commented that as far as
she could see this fell to the Committee.
Supporter
Councillor
Penfold advised that she had nothing further to say.
Objectors and Representative
All
the other parties present confirmed that they had nothing further to say.
The
Chair established from all those parties in attendance at this point that they
had received a fair hearing.
In
terms of the Councillor’s National Code of Conduct Councillor Gemma Penfold
left the meeting at this point.
DEBATE
Councillor
Kennedy referred to the concerns raised about possible flood risk. He said he did not doubt the calculations
made but commented that something was not working properly due to the flooding
experienced right now. He acknowledged
the mitigation measures that would be put in place but said the residents were
genuinely afraid of being inundated with water.
He said that he did not think the developer had satisfied the conditions
and mitigated for all possible future flooding.
He also referred to input from SEPA and Scottish Water being
missing. He advised that the general
picture was Cardross was being flooded.
He said that he had no problem with a new housing estate but for things
on the outside it may mean spending money to get a solution, spending money on
the infrastructure round and about. He
suggested it might need the Council to put money in to redesign the area so the
floods could be avoided.
Councillor
Irvine advised that he had concerns that no permission had been granted by the
landowner. He said that as someone who
had studied climate change, he was worried that the last involvement of SEPA
was 9 years ago and commented that they would have a lot more information
regarding the impact of climate change now.
He said he was concerned about not having up to date key pieces of
information.
Councillor
Howard said she was concerned about the piece of land the burn was on. No permission had been obtained to use it and
there was a danger of damaging the burn banks.
She advised that she did not think research had been done into that as
well as the Skunk Cabbage issue which was just starting to gather there and
would not have been there 9 years ago.
She said this was not the developer’s fault but was an issue that needed
to be dealt with.
Councillor
Kain referred to all the discussions. He
said that climate change was a fact and was constantly changing. He commented that the main objection was the
flood risk and said that there has been flooding here long before this proposed
development was ever planned. He pointed
out that the developer had said this development would reduce the effect of
flooding in the immediate area and that they would also be addressing the
failure of the previous development. He
said he could not see a reason to object on grounds of the current flooding as
that was going to be alleviated by the development. He also referred to the serious issue of the
lack of housing and advised that he would be in favour of this development.
Councillor
Hardie advised that he lived in Cardross and had seen the flooding for himself
and he said it was horrendous. He said
that he felt a development of this size would not make it better and that he
believed it could get worse. He referred
to comments about SEPA and said he was not sure if they would look at it again.
Councillor
Irvine referred to comments by Councillor Kain about the importance of housing
development in terms of the need to meet the housing emergency and said that
was never in question. He said that he
was in a situation where there were gaps in his knowledge and a lack of clarity
about the additional water which he perceived to be channelled into the pond or
burn which was already under serious pressure from existing water flooding. He said he was worried about that water being
directed in a controlled manner into the burn.
From what he could see this was taking a problem and moving it
sideways. He said he would like more
clarity on how that would be managed. He
said that he agreed that there was a need for an economic boost to the area but
the issue for him was the diversion of water to an area of land where no
permission from the landowner had been received. He also said he had not seen any sign of the
modelling matching the reality and that he had a big concern about that.
Councillor
Brown said she was not against the houses and not against the plan and she did
not doubt the report the Applicant had in respect of the modelling carried
out. However, having not heard from
Scottish Water about the environmental issues and land ownership, she said this
did not sit comfortably with her. She
was also had concerns about SEPA not being consulted.
Councillor
Philand echoed the concerns raised by Councillor Brown. He said the big thing for him was SEPA and
questioned whether the Committee could ask them to look at the design. He advised that he also had concerns about
the confirmation the Chair had received in the respect of the installation of
the missing pipework from the previous development, that if that design was for
a new development now it would not be approved.
Councillor
Blair said he took a more pragmatic view of the discussions heard. He commented that the rain would be managed
better with the mitigation proposed. He
said he understood the angst of the local residents. He said he did not know if SEPA would engage
or not. He said he was minded to support the Officer’s recommendation fully
taking on board the concerns about processes and the horticultural aspects and
the issue of offloading water onto someone else’s land and commented that this
may be out with the Committee’s remit. He said the Committee were here to
discuss the parameters of the application and that he had taken on board the
angst of the local residents. He
referred to the bureaucracy of other organisations. He said that as it stood at the moment he was
minded to support the Officer’s recommendation.
Councillor
Green commented that he thought there was a number of difficult issues. He said he welcomed a private developer
building in Argyll and Bute and that it was good to have investment to help
address the housing emergency. He
advised that he had every confidence with what the developer had proposed for
what was in their control and that they had done everything they could to
address the issues of rainfall and drainage.
He advised that the difficulty for him was the areas where rain fall was
out with their control, that interaction and how it all worked together was
difficult to see. He said he was not
sure how many years ago Kilmahew had been built and that if the missing
pipework had been in place from then there would have been a better idea of the
impact it had on the burn. He advised
that the problem with putting the two things together this information was not
known. He said he felt that the
Committee were being asked to approve an application for housing and also the
side effect of improving flooding in large parts of the village. He said it would be difficult if it improved
the flooding for the large part of the village but made it worse for a handful of
houses. He said it was easy to make
decisions on planning applications and weigh up issues in respect of landscape,
visual amenity, noise and economic impact.
He said it could be recognised that with a new development you may get a
loss of visual amenity but when it came to the potential for an increased risk
of flooding that was more difficult. He
said he was not entirely confident of the best way forward and welcomed the
input of the other Members.
Councillor
Kennedy said there was an expensive solution.
He questioned why a wider pipe could not be put in when digging up the
road. He said that could be one solution
to the problem. He said he thought there
would be a way to do it properly rather than tinkering around the edges.
Councillor
Blair said it was about engagement with the professional developers and
Planners to come up with the answers and he thought they had come up with the
answers. He said the knock on effect was
out with this application and could not necessarily be controlled for this
process.
Councillor
Kennedy questioned what would happen if the development had a big effect on
what happened out with it. He said the
flood prevention in Cardross was not working at the moment and that it was
going to be exacerbated with climate change.
Councillor
Blair said that the volume of water that landed on the footprint of the estate
would be the same as landing on the roofs.
To his mind it was the same volume of water. He said the mitigation proposed would see an
improvement but would not resolve the other issues. He said the Committee had to look at this in
terms of the planning application. He
added that this was not to say he was not concerned about a holistic approach.
Councillor
Brown questioned how the Committee could take this forward as they needed to be
confident that they would be improving the situation. She said it had to be bigger than just one
application. She acknowledged that the
Committee were looking at one application but said that the flooding issue was
huge and asked if this could be taken to another forum.
Councillor
Blair said it would need to be taken to another forum and that the Committee
needed to focus on the application. He
said that he had been impressed by the presentations by the community and
advised that he would be happy to raise issues with his MP and MSP. He said it was all about partnership working.
Councillor
Howard acknowledged that the Committee needed to look at the application. She said that if it was granted now it would
be too late to get the answers the Committee were looking for. She said the application needed to be put on
hold in order to get the answers to how to stop the burn flooding.
Councillor
McCabe said that the Committee were not the flooding experts. She advised that the flood risk adviser to
the Council had agreed that this could go ahead. She also advised that this would allow for
much needed housing to be built. She
noted that the developer would try to solve the problem and not make it
worse. She noted that they had spoken to
Scottish Water and that they have given the Committee a lot of information.
Councillor
Irvine advised that for him there was three gaps – no input from the
landowners; no definite input from SEPA since 2015; and no discussion from
Scottish Water. He said it was not about
more water but about the redirection of water which, he thought, would have an
impact. He said he would find it
difficult to make a decision on this with these gaps and that he would like
more detail around these grey areas – Scottish Water plan and input from SEPA
and landowners. He said that he totally
supported the development and had no qualms about working with the developers
and partners to find a solution but until he saw that solution, he advised he
could not support this application.
Councillor
Blair proposed supporting the recommendations and to also receive guidance on
whether or not other conditions could be added in the sense of receiving
confirmation from the bodies Councillor Irvine referred to.
David
Logan advised that it would not be competent for Councillor Blair to move the
granting of the Officer’s recommendation then ask for further clarity.
Motion
To
agree to support the Officer’s recommendation as set out at part 3 of
supplementary report number 1.
Moved
by Councillor Gordon Blair, seconded by Councillor Andrew Kain.
Amendment
To
agree to continue consideration of this application to a future meeting of the
Committee to allow Members time to prepare a competent Motion to either refuse
the application or seek clarity on specific matters from third parties on
issues raised during the meeting.
Moved
by Councillor Mark Irvine, seconded by Councillor Paul Kennedy.
A
vote was taken by calling the roll.
Motion Amendment
Councillor
Blair Councillor
Brown
Councillor
Kain Councillor
Green
Councillor
McCabe Councillor
Hardie
Councillor
Wallace Councillor
Howard
Councillor
Irvine
Councillor
Kennedy
Councillor
Philand
The
Amendment was carried by 7 votes to 4 and the Committee resolved according.
DECISION
The Committee agreed to continue
consideration of this application to a future meeting of the Committee to allow
Members time to prepare a competent Motion to either refuse the application or
seek clarity on specific matters from third parties on issues raised during the
meeting.
(Reference: Report by Head of Development and Economic Growth dated 7 March 2024 and supplementary report number 1 dated 13 June 2024, submitted)
Supporting documents: