An interim progress report covering the audit work performed by Internal Audit as at 24 May 2013 was considered.
Decision
Approved the progress made with the Annual Audit Plan for 2013 – 2014.
(Reference: Report by Chief Internal Auditor dated 29 May 2013, submitted)