A816 Cuilfail Hotel Bridge, Kilmelford

Phase 2 works have begun on A816-110 Cuilfail Hotel Bridge, Kilmelford, which means that traffic management (portable traffic lights) will be in place until works are complete. There is no weight restriction in place.

Update: 19 December 2024

Access

Traffic Management (portable traffic lights) are in place at A816 Cuilfail Hotel Bridge, Kilmelford, until Phase 2 works are completed.

No weight restriction is currently in place.

Key dates

Phase 1 - completed:

  • On 19/10/2023 the bridge was found to be severely damaged following two October 2023 weather events and it was demolished the same day,
  • The bridge was urgently replaced through emergency procedures and on 30/10/2023 was reopened to vehicles with a 3t MGW restriction,
  • On 02/11/2023 the 3t MGW weight restriction was removed from the bridge,

Phase 2 - underway:

  • Phase 2 works were able to follow a more traditional, non-emergency, design and consents process, and site works commenced 19/08/2024.
  • The majority of site works are programmed for completion in January 2025 although some works are subject to additional SEPA Licencing and cannot be carried out until Summer 2025.
  • Contractor shall be off site over the Christmas 2024 closedown period. The site will be left in a safe condition until 06/01/2025 when the Contractor returns to site.
  • Final elements of the Phase 2 works will be completed during January 2025.

Phase 3 - Summer 2025

  • Final phase of works to upstream north embankment are programmed for a circa five-week period of works during Summer 2025.

 

Image
The new Kilmelford Bridge

The newly built and opened bridge at Kilmelford on 2 November 2023.

 

Kilmelford Bridge

Kilmelford Bridge

Kilmelford Bridge