Roads Capital Programme 2024/25

Helensburgh and Lomond surface dressing and bituminous surfacing schemes 2024/25

Programme status key
Description Status
SCHEME PROGRAMMED TO BE DELIVERED - ( Approximate duration and START month indicated ) Scheduled
SCHEME UNDERWAY - WORK IN PROGRESS -  (Traffic Management as required, during works) In progress
WORKS ONSITE SUBSTANTIALLY COMPLETE. ( Road Markings and White Lining - Weather permitting ) Complete

Last updated - 28th June 2024

Helensburgh and Lomond

Carry over budget from 2023/24

Helensburgh and Lomond carry over from 2023/24
Location Treatment type Duration - Days Start Month Status
A814 (@ Haul Road - A817) Middle roundabout Kerbing  and surface 5 Aug-24 Scheduled

Surface dressing and preparation

Helensburgh and Lomond surface dressing and preparation
Location Treatment type Duration - days Start month Status
2024 Pre -SD A814 - sites below Pre-SD 2024 30 Apr-24 Complete
A814 - Whistlefield to Finnart Laying 2024 3 Jun-24 Complete
A814  - South of Glen Douglas Laying 2024 3 Jun-24 Complete
2025 Pre-SD  Pre-SD 2025 20 Apr-24 Complete

Bituminous surfacing etc.

Helensburgh and Lomond bituminous surfacing
Location Treatment type Duration - days Start month Status
 C 69 Glen Douglas hairpin bends to A82  Overlay 5 Jun-24 Complete
 B832 Muirlands  - Cross keys - A82  (5 SITES) Overlay 10 Jun-24 Complete
 U71 Colqhoun st   W Argyle st - W King St inlay 5 Sep-24 Scheduled
 U262  Shore road - Helensburgh    PH 1  inlay 10 Aug-24 Scheduled
 U177 Kirk Brae - Shandon inlay 5 Aug-24 Scheduled
 U72 Columba St - Helensburgh inlay 5 Sep-24 Scheduled
A814 Whistlefield Roundabout  kerb & surface 5 Aug-24 Scheduled
 U 306 Victoria Road - Helensburgh  inlay 10 Oct-24 Scheduled
 U105 East Prices st   Henry Bell st -  Geo St inlay 15 Sep-24 Scheduled
 B872  Whistlefield road - Garelochead inlay 10 Jul-24 Scheduled
 U62  Church Road - Rhu inlay 5 Sept-24 Scheduled
 U101 East King - Charlotte St to Grant st inlay 5 Sep-24 Scheduled
 U13 Ardencaple Quadrant  inlay 10 Aug-24 Scheduled
 U133 Forestry Houses - Succoth (Loch Long) inlay 5 Jul-24 In Progress
 A817 Haul Rd  @  A814 Roundabout  - High Friction Surface Treatment 2 Aug-24 Scheduled
Did you find what you were looking for?

Why wasn't this information helpful

Limit to 250 characters.